The 28-Day Notice That Decides FIDIC Claims in Trinidad and Tobago
In January 2026 the Privy Council overturned a TT$13.9 million Court of Appeal judgment for a contractor on a WASA pipeline, partly because no notice of claim was given within 28 days.
By caribbean.law

In 2007 the Water and Sewerage Authority hired Uniform Building Contractors to design and lay more than 28 kilometres of pipeline from Rio Claro to Mayaro. The contract used the FIDIC Yellow Book, the international standard form for design-and-build work. By 2009 the relationship had ended in termination. The contractor later sued for extra work it said it had been told to do: laying pipe in the roadway, removing unsuitable soil, bringing in new backfill and working at night.
The Court of Appeal awarded it TT$13.9 million. On 22 January 2026 the Privy Council reversed that decision and dismissed the claim. The disputed work was not a variation, meaning a change to the agreed work that earns extra payment. Even if it had been, the contractor never made a claim within the 28 days the contract allowed. The decision in Uniform Building Contractors v WASA binds the courts of Trinidad and Tobago on any contract that keeps the standard clause 20.1.
Why the Privy Council rejected the WASA pipeline claim
The Privy Council first held that the Engineer's opinion cannot turn contract work into a variation. The Engineer is the contract administrator the employer appoints to run the project, and here he gave evidence for the contractor that he regarded the four items as variations. Giving the judgment, Sir Peter Coulson said that view "cannot displace the proper application of the terms of the contract". Whether work is extra is a question for the contract documents, and here they already required the work.
Clause 20.1 of the 1999 FIDIC form makes a 28-day notice a condition of payment. It requires notice no later than 28 days after the contractor "became aware, or should have become aware" of the event. If that window is missed, the employer is discharged from liability. The Board called the wording "classic condition precedent form", meaning a step that must be taken before any right to payment exists. The contractor knew about the four items by the end of 2007 and gave no clause 20.1 notice.
Ending the contract did not revive the claim. The Court of Appeal had reasoned that termination freed the contractor from clause 20.1. The Board disagreed: termination works forwards rather than backwards and "could not in law resurrect claims that had not been made in time".
Nor could the Engineer waive the procedure. The contractor said WASA had waived it through the Engineer's conduct. Only the employer can waive a term of its own contract, and the Engineer had no power to amend it. The point had not even been pleaded.
The Privy Council also relied on its 2015 decision in NH International v NIPDEC, another FIDIC dispute from Trinidad and Tobago. There it held that an employer's set-offs count only if notified under clause 2.5, the employer's own claims clause.
What the 2017 FIDIC forms change
Most local disputes so far have arisen under the 1987 and 1999 editions. Projects funded by the World Bank and other lenders now use bidding documents built on the 2017 editions. These keep the 28-day rule and tighten what follows it.
| 1999 forms | 2017 forms | |
|---|---|---|
| Notice of claim | Within 28 days of awareness (clause 20.1) | Within 28 days of awareness (Sub-Clause 20.2) |
| Fully detailed claim | Within 42 days; lateness does not cancel the notice | Within 84 days; without its legal basis the notice lapses |
| Late notice | Fails unless the employer waives it | Stands unless the Engineer objects within 14 days; prejudice and prior knowledge can excuse it |
| Employer claims | Clause 2.5, notice "as soon as practicable" | Same clause and same 28 days as the contractor |
The 2017 review of a late notice is narrow. It happens when the claim is decided, and the starting point is still that a late claim fails.
Keeping a claim alive on a state project
WASA, NIDCO and UDeCOTT have all contracted on FIDIC terms. A public body is unlikely to waive its own procedures, so a contractor can protect a claim with five habits.
The date of awareness. The clock starts when the contractor knew or should have known of the event, not when the cost became clear. Record that date when it happens.
Notice while the problem is ongoing. The Board described clause 20.1 as an early warning that applies "even if the situation that gave rise to the claim was ongoing". A short notice now preserves a claim that a full submission later cannot rescue.
Instructions in writing. A conversation on site with the Engineer is not a variation. Ask for the written instruction. Where the contract provides for one, also ask for the Engineer's determination: a formal written decision on the claim.
No reliance on reassurance. An Engineer who says the paperwork can follow has no authority to excuse it. Only the employer can excuse it, and that waiver would have to be proved.
Records from the first day. In the WASA case there was "an almost complete absence of contemporaneous documents" about how the disputed work came about.
Contracts with state bodies carry their own public-law deadlines and limits, and the first weeks of a dispute often shape how it ends.
Frequently asked questions
Can a late FIDIC notice ever be accepted? Under the 1999 forms, only if the employer itself waived the requirement, and that has to be pleaded and proved. The 2017 forms add a review that weighs prejudice and the other side's prior knowledge. The starting point is still that a late claim fails.
Does the 28-day rule apply to employers? Not under the 1999 forms, which ask the employer for notice "as soon as practicable" under clause 2.5. The Privy Council held in NH International v NIPDEC in 2015 that an employer's claim made without that notice fails. The 2017 forms apply the same 28 days to both sides.
What if the Engineer instructed the work verbally? The contract decides whether work is a variation; an instruction alone does not. If the Engineer does not deal with a genuine variation, the contractor's route is a clause 20.1 claim within 28 days.
On a FIDIC contract the work that decides payment happens in the first month after a problem appears. By the time arbitration under the 2023 Act or a court hearing begins, the notice has either been given or it has not.